£500,000
Project Details
CLIENT
COST
OVERVIEW
The Holywood Sewers Scheme was a significant project aimed at alleviating complaints of sewage odour around Holywood, Co. Down. This project involved a major programme of sewer laying, tunnelling, and the construction of a pumping station, measuring 10 meters in diameter and 12 meters in depth. The new pumping station was designed with two compartments: one for storm water and one for foul water, with the capacity to deliver flows of 220 l/s for storm water and 860 l/s for foul water. This solution addresses the issues faced by local residents while ensuring the efficient handling of wastewater.
SCOPE OF SUPPLY
FME was responsible for the M&E works involved in the project, which included the supply, installation, and commissioning of the following key equipment:
Key M&E Equipment Supplied:
- 4 No. 22kW Foul Xylem Submersible Pumps (220 l/s)
- 4 No. 37kW Storm Xylem Submersible Pumps (860 l/s)
- Local Isolation Stations
- EN 598 Delivery Pipework (DN400 / DN700)
- DN400 / DN700 Gate Valves & Non Return Valves
- DN400 / DN700 Flowmeters (M-Cert)
- Actuated Penstocks (1200mm * 1200mm)
- 2 No. 316 St. St. Hydrok Peak Screens each capable of dealing with 860 l/s
- Washwater Booster System
- 1.5T @ 10m Pillar Jib Crane
- NIW SS200E Form 4 Control Panel with Telemetry Integration (SS200E & SS232E)
- GRP Control Kiosk (7m Long)
- Ultrasonic Level Controls
- Site and Chamber Lighting
This installation ensures reliable wastewater management, contributing to improved environmental quality and better public health outcomes in the Holywood area.